The state of the worksite

Each worksite has a status which indicates the current progress of the worksite. You can manually change thecondition of a worksite when it is not yet part of a schedule. Subsequently, the site will change status automatically to indicate that the work has started, completed or a problem has occurred on the site. A color indicator allows you to quickly know the state of your site in order to provide information to the dispatcher.

Change the state of the site

  1. From theHome | Site planning | Worksite schedule

  2. Select a site and carry out a right mouse click to display the menu

  3. Go to Site parameters

  4. Go to Condition of the worksite

  5. Choose the state of this site

Change the state of a worksite sequence:

The change to a state of a construction sequence only operates on an individual day.


Add a worksite status note

  1. From theHome | Site planning | Worksite schedule

  2. Select a site and carry out a right mouse click to display the menu

  3. Go to Site parameters

  4. Click on Site condition note

  5. Click in the field Note and type your note

  6. Click on To modify to save

  7. A note icon will be displayed in the icon column of your site

Hover your cursor over the icon to see the message.


Edit a construction status note

  1. From theAccueil | Planification de chantier | Horaire des chantiers

  2. Select a site and carry out a right mouse click to display the menu

  3. Go to Site parameters

  4. Click on Site condition note

  5. Click in the field Note and edit your rating

  6. Click on To modify to save

  7. A note icon will be displayed in the icon column of your site


Delete a construction status note

  1. From theHome | Site planning | Worksite schedule

  2. Select a site and carry out a right mouse click to display the menu

  3. Go to Site parameters

  4. Click on Site condition note

  5. Click in the field Note and delete your note

  6. Click on To modify to save

  7. L'note icon will disappear