Before finalizing the steps for creating a worksite, you must assign a project for a worksite. The projects contain important information for the completion of the site (information on the customer; information on the contacts and general site information).
Creation of projects
Create a project
-
From theHome | Site planning | Worksite schedule
-
You arrive on the timetable
-
Create a worksite or a construction sequence
-
In the area Site information, click on the button Choose a project
-
On the right side of the bar Research, you notice the symbol ➕. Click on this one
-
Fill in the fields and press Create
-
To save the information, complete the fields in the box Logistics and press Apply
-
Press Close to exit the window
Before you finish creating the project, you can edit the field Reference number to enter your reference code.
Edit a project
-
From theHome | Site planning | Worksite schedule
-
You arrive on the timetable
-
Select the existing site and go to the function To modify
-
Just above Logistics, you have the project name. Click on this one
-
To the right of the project phase, you see a pencil icon. Tap it to make changes
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Creating a customer
Create a customer
-
During project creation, you have an area Customer
-
In the field Customer, you notice the symbol ➕. Tap this one
-
Fill in the fields and click Apply when you are finished
Edit customer information
-
From theHome | Site planning | Worksite schedule
-
You arrive on the timetable
-
Select the existing site and go to the function To modify
-
Just above Logistics, you have the project name. Click on this one
-
To the right of the project phase, you see a pencil icon. Tap it to make changes
-
Go to the zone Customer
-
In the field Customer, press pencil icon to modify the information
-
Edit the information and click Apply to save
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Change a client for another client
-
From theHome | Site planning | Worksite schedule
-
You arrive on the timetable
-
Select the existing site and go to the function To modify
-
Just above Logistics, you have the project name. Click on this one
-
To the right of the project phase, you see a pencil icon. Tap it to make changes
-
Go to the zone Customer
-
In the field Customer, press the ✖ button to clear the present client
-
Click the empty field of Customer and press one letter or the up/down arrow on the keyboard to display the list. THE diagonal arrows (next to ➕) give access to the search for an existing customer
-
Select the desired customer
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Creating a contact
Create a contact
-
During project creation, you have an area Contacts
-
In the field Contact, you notice the symbol ➕. Tap this one
-
Fill in the fields and click Apply when you are finished
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Edit contact information
-
From theHome | Site planning | Worksite schedule
-
You arrive on the timetable
-
Select the existing site and go to the function To modify
-
Just above Logistics, you have the project name. Click on this one
-
To the right of the project phase, you see a pencil icon. Tap it to make changes
-
Go to the zone Contacts
-
In the field Contact, press pencil icon to modify the information
-
Edit the information and click Apply to save
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Add other contacts
-
From theHome | Site planning | Worksite schedule
-
Select the existing site and go to the function To modify
-
Just above Logistics, you have the project name. Click on this one
-
To the right of the project phase, you see a pencil icon. Tap it to make changes
-
Go to the zone Contacts
-
Press + Add a relationship
-
A new field is added to the area Contacts
-
You can add an existing contact by clicking in the empty field or create a new contact
-
Choose the role of your contact in the field Role
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Remove a contact
-
From theHome | Site planning | Worksite schedule
-
Select the existing site and go to the function To modify
-
Just above Logistics, you have the project name. Click on this one
-
To the right of the project phase, you see a pencil icon. Tap it to make changes
-
Go to the zone Contacts
-
Place your cursor on the field Role, a ✖ appears
-
Click on this one and respond Yes to remove the contact
-
Press To safeguard to save changes
-
Click on Apply to keep the information. Then tap Close to return to the construction schedule
Mandatory field :
When you see an asterisk in a field, this area is required to be completed.