Schedule day settings

Cactusoft Construction allows you to modify several elements related to the worksite on a daily basis. For example: public holiday, worker absent.

Put a worker away

  1. From theHome | Site planning | Worksite schedule

  2. In the timetable, you have a header with a date. Click on the date where the worker will be absent. The menu will be displayed

  3. Select Edit info for the day

  4. Click on Workers to display the areas

  5. In the area Absent workers, click on the empty field to display the names of your absent workers

  6. Select the name of the absent worker. If necessary, you can press the diagonal arrows to search for the worker's name

  7. Press Confirm to save the information


Put an irregular worker

  1. From theHome | Site planning | Worksite schedule

  2. In the timetable, you have a header with a date. Click on the date and the menu will be displayed

  3. Select Edit info for the day

  4. Click on Workers to display the areas

  5. In the area Irregular workers, click on the empty field to display the names of your irregular workers

  6. Select the name of the irregular worker. If necessary, you can press the diagonal arrows to search for the name of the irregular worker

  7. Press Confirm to save the information

To have a list of irregular workers, your workers must be idle. Visit the page The status of an employee to modify the status of your employee and the page Employee status for the detailed list of statuses.


Put on a holiday

  1. From theHome | Site planning | Worksite schedule

  2. In the timetable, you have a header with a date. Click on the daytime holiday

  3. The menu will appear, select Edit info for the day

  4. Activate the button Set as holiday

  5. Press Confirm to save the information. A icon will appear next to the selected day